Project Tag: Block M, Plot 315 – Location: MBZC


  • 08-06-2026 — Site Visit — M/315 MBZC

    Comprehensive site visit report for Villa M-315 in MBZC, Fujairah, evaluating the 68% complete structure under Seven Star Building Contracting. This audit details essential corrections for external stone cladding modifications, MEP pipe concealment, sunken area clearance, and immediate safety handrail installations to optimize high-end villa construction in UAE

  • 30-04-2026 — Site Visit — M/315 MBZC

    Site visit report for Villa M-315 in Fujairah detailing the progress of ceramic works, first-floor painting, and septic tank initiation. Includes critical directives for external decor modification, bitumen removal, and proper sequencing of finishing tasks to ensure high-quality villa construction in UAE.

  • 26-03-2026 — Site Visit — M/315 MBZC

    Engineer Adeel Arif reports Villa M-315 MBZC is ready for stone works. The bitumen on the complete villa is finished, providing a waterproof base for the owner’s cladding. While inside plaster is completed and primer paint is underway, the boundary wall remains pending due to a shortage of blocks in Fujairah.

  • 23-11-2025 — Site Visit — M/315 MBZC

    Construction update for M-315 MBZC: A major milestone has been reached with the completion of blockworks for the whole villa. Internal walls are now fully prepped and ready for plaster. Simultaneously, construction of the parapet walls and roof-level decor works is actively ongoing.

  • 18-11-2025 — Site Visit — M/315 MBZC

    Engineer Adeel Arif reports MBZC Plot 315 Block Work is accelerating, now 85% complete after new blocks arrived. An AC relocation in the Gents Majlis requires core cutting due to a missing AC sleeve, adding cost. Consultant informed Owner for decision.