Project Tag: Block G, Plot 549 – Location: Mohamed Bin Zayed City


  • 01-06-2026 — Site Visit — G/549 MBZC

    Professional site engineer report detailing the near-completion of outside walls bitumen repairing work and manhole installations for a villa in MBZC, Fujairah. This technical review highlights internal floor piping progress, structural readiness for upcoming external stone works, and material logistics management regarding pending ceramic deliveries.

  • 04-04-2026 — Site Visit — G/549 MBZC

    We are elevating the aesthetics! The external stone work is currently transforming the facade, while inside, our team is hard at work on the premium ceramic installations. Quality control is our priority—today we verified the precision of concealed WC cisterns and decorative wall niches to ensure a sleek, modern finish in every bathroom. We are…

  • 30-03-2026 — Site Visit — G/549 MBZC

    Engineer Adeel Arif reports external stone work is 50% complete at MBZC Villa G-549. However, extreme rains have caused water leakage through slabs and AC sleeves, leading to damaged inside walls primer. Remedial repairs and waterproofing are now prioritized alongside ongoing bathroom and kitchen ceramic work in Fujairah.

  • 03-03-2026 — Site Visit — G/549 MBZC

    Engineer Adeel Arif reports bitumen works are underway at MBZC Villa G-549, preparing the facade for stone works. Inside, bath and kitchen ceramics are nearly finished. With the remaining ceramic materials on order and electrical wiring in progress, the villa is rapidly advancing in Fujairah.

  • 12-01-2026 — Site Visit — G/549 MBZC

    Engineer Adeel Arif reports MBZC Villa G-549 is nearing the stone works phase. Outside drainage pipes and manhole works are almost complete, and all boundary wall columns have been casted. Site is awaiting a consultant review on final architectural modifications to ensure smooth progress in Fujairah.