Project Tag: Block G, Plot 425 – Location: Mohamed Bin Zayed City


  • 13-01-2026 — Site Visit — G/425 MBZC

    Engineer Adeel Arif reports tie beam shuttering is nearly complete at MBZC Villa G-425 following the completion of solid blocks up to tie beam. A technical conflict between decor and bath piping was proactively discussed with the consultant to ensure future maintenance-free pipe placement in Fujairah.

  • 13-01-2026 — Site Visit — G/425 MBZC

    Engineer Adeel Arif reports good progress at MBZC Villa G-425. The shuttering for 10 cm PCC is complete and ready for casting. This layer provides the base for solid block work below tie beam, marking a key transition in the substructure phase in Fujairah.

  • 05-01-2026 — Site Visit — G/425 MBZC

    Engineer Adeel Arif confirms MBZC Villa G-425 has completed neck column and block works below tie beam. Backfilling of soil is now finished, and the site is preparing to start tie beam shuttering. All materials are safely within plot limits as the project regains momentum in Fujairah.

  • 28-12-2025 — Site Visit — G/425 MBZC

    Site update for MBZC Villa G-425: Neck column casting and solid block work below tie beam are complete. Engineer Adeel Arif has directed the start of bitumen coating and issued strict site clearance orders for materials and debris to prepare for the upcoming backfilling phase.

  • 14-12-2025 — Site Visit — G/425 MBZC

    Engineer Adeel Arif reports work restart at MBZC Villa G-425. Construction was stopped due to a severe delay in solid blocks delivery post-footing casting. Blocks have now arrived, and the team is instructed to accelerate work to recover lost time in Fujairah.