Engineer Adeel Arif confirms MBZC Villa G-425 has completed neck column and block works below tie beam. Backfilling of soil is now finished, and the site is preparing to start tie beam shuttering. All materials are safely within plot limits as the project regains momentum in Fujairah.
Site update for MBZC Villa G-425: Neck column casting and solid block work below tie beam are complete. Engineer Adeel Arif has directed the start of bitumen coating and issued strict site clearance orders for materials and debris to prepare for the upcoming backfilling phase.
Engineer Adeel Arif reports work restart at MBZC Villa G-425. Construction was stopped due to a severe delay in solid blocks delivery post-footing casting. Blocks have now arrived, and the team is instructed to accelerate work to recover lost time in Fujairah.
Engineer Adeel Arif reports foundation work is complete at MBZC Villa G-425. Curing is ongoing, and neck column shuttering preparation has begun. However, the site is currently waiting for the delivery of block work material to start the work for Tie Beam and Neck Column.
Engineer Adeel Arif details foundation readiness at MBZC Villa Plot 425 following successful Natural and Road Base Density Tests. PCC shuttering is complete, with directives issued for 10 cm PCC thickness, mandatory Termite Treatment, and site cleanliness before casting.