Engineer Adeel Arif reports work restart at MBZC Villa G-425. Construction was stopped due to a severe delay in solid blocks delivery post-footing casting. Blocks have now arrived, and the team is instructed to accelerate work to recover lost time in Fujairah.
Engineer Adeel Arif reports foundation work is complete at MBZC Villa G-425. Curing is ongoing, and neck column shuttering preparation has begun. However, the site is currently waiting for the delivery of block work material to start the work for Tie Beam and Neck Column.
Engineer Adeel Arif details foundation readiness at MBZC Villa Plot 425 following successful Natural and Road Base Density Tests. PCC shuttering is complete, with directives issued for 10 cm PCC thickness, mandatory Termite Treatment, and site cleanliness before casting.