Project Tag: Block G, Plot 420 – Location: Mohamed Bin Zayed City


  • 14-12-2025 — Site Visit — G/420 MBZC

    Engineer Adeel Arif reports work is slow at MBZC Villa G-420 due to block delivery delays. Boundary Wall excavation is underway on three sides, despite complications from a neighboring villa construction. Site instructs acceleration and urgent follow-up on block delivery status.

  • 25-11-2025 — Site Visit — G/420 MBZC

    Engineer Adeel Arif reports a critical slowdown at MBZC Villa G-420; little work has been done since the First Floor Slab casting (28 days). The site is now initiating Boundary Wall works and cleaning the perimeter area to resume progress.

  • 08-11-2025 — Site Visit — G/420 MBZC

    Engineer Adeel Arif reports on the post-casting phase at MBZC Plot 430, Fujairah. The First Floor Slab, cast on Oct 25th, is now undergoing controlled de-shuttering. Site is focused on proper concrete curing and preparing for the next phase of block work.

  • 23-10-2025 — Site Visit — G/420 MBZC

    Engineer Adeel Arif reports on the successful Fujairah Municipality inspection for Villa G/420 MBZC. The First Floor Slab received conditional approval for casting, with the FM Engineer appreciating site safety and steel works. After a quick signboard update, full concrete casting approval was secured, ensuring project progress.

  • 20-10-2025 — Site Visit — G/420 MBZC

    Engineer Adeel Arif’s latest site report confirms the successful completion of the First Floor Slab steel works for the villa in MBZC Plot 549, Fujairah. All reinforcement aligns with approved drawings, and crucial safety measures, including temporary external stairs, are now in place as per Fujairah Municipality regulations. The site is prepared for consultant and…