Engineer Adeel Arif reports that parapet decor works are in progress at MBZC Villa G-420. While ground floor block work reached 10%, it is currently halted due to a block work supply shortage. Site cleaning is underway to start boundary wall excavation and maintain project momentum in Fujairah
SITE VISIT REPORT: ARCHITECTURAL LAYOUT VERIFICATION & BOUNDARY PREP Project Name: Proposed Villa Location: Block G, Plot 420, Mohammed Bin Zayed City (MBZC), Fujairah Date of Visit: January 05, 2026 Time of Visit: 11:30 AM Report Prepared By: Engineer Adeel Arif (Site Engineer) ____________ I. Purpose of Visit: To verify the initial layout of the…
Site update for MBZC Villa G-420: Parapet wall reinforcement is underway with a consultant inspection pending for the upcoming concrete cast. Engineer Adeel Arif has directed immediate Fosroc repairs for concrete honeycombing and addressed block work delays caused by supplier issues.
Engineer Adeel Arif reports work is slow at MBZC Villa G-420 due to block delivery delays. Boundary Wall excavation is underway on three sides, despite complications from a neighboring villa construction. Site instructs acceleration and urgent follow-up on block delivery status.
Engineer Adeel Arif reports a critical slowdown at MBZC Villa G-420; little work has been done since the First Floor Slab casting (28 days). The site is now initiating Boundary Wall works and cleaning the perimeter area to resume progress.