Project Tag: Block G, Plot 420 – Location: Mohamed Bin Zayed City


  • Engineer Adeel Arif reports that parapet decor works are in progress at MBZC Villa G-420. While ground floor block work reached 10%, it is currently halted due to a block work supply shortage. Site cleaning is underway to start boundary wall excavation and maintain project momentum in Fujairah

  • 05-01-2026 — Site Visit — G/420 MBZC

    SITE VISIT REPORT: ARCHITECTURAL LAYOUT VERIFICATION & BOUNDARY PREP Project Name: Proposed Villa Location: Block G, Plot 420, Mohammed Bin Zayed City (MBZC), Fujairah Date of Visit: January 05, 2026 Time of Visit: 11:30 AM Report Prepared By: Engineer Adeel Arif (Site Engineer) ____________ I. Purpose of Visit: To verify the initial layout of the…

  • 28-12-2025 — Site Visit — G/420 MBZC

    Site update for MBZC Villa G-420: Parapet wall reinforcement is underway with a consultant inspection pending for the upcoming concrete cast. Engineer Adeel Arif has directed immediate Fosroc repairs for concrete honeycombing and addressed block work delays caused by supplier issues.

  • 14-12-2025 — Site Visit — G/420 MBZC

    Engineer Adeel Arif reports work is slow at MBZC Villa G-420 due to block delivery delays. Boundary Wall excavation is underway on three sides, despite complications from a neighboring villa construction. Site instructs acceleration and urgent follow-up on block delivery status.

  • 25-11-2025 — Site Visit — G/420 MBZC

    Engineer Adeel Arif reports a critical slowdown at MBZC Villa G-420; little work has been done since the First Floor Slab casting (28 days). The site is now initiating Boundary Wall works and cleaning the perimeter area to resume progress.