Project Tag: Block F, Plot C2 (SHOPS) – Location: Mohamed Bin Zayed City


  • 03-04-2026 — Site Visit — F/C2 (SHOPS) MBZC

    The foundation is set, and now we rise! With the grade slab complete, our team is currently focusing on the ground floor columns. We’ve conducted rigorous checks on steel reinforcement overlaps and stirrup spacing to ensure maximum structural stability. 3 columns are already standing tall, and the rest are in progress. Quality engineering is the…

  • 24-03-2026 — Site Visit — F/C2 (SHOPS) MBZC

    Engineer Adeel Arif reports successful Fujairah Municipality inspection for F C2 Shops. Grade slab steel and bitumen sheet placement were approved by FM Engineer Anwar. While substructure is ready for concrete casting, the team is addressing external debris through the FM online system to ensure plot limit compliance.

  • 19-01-2026 — Site Visit — F/C2 (SHOPS) MBZC

    Update for Villa F-C2, MBZC: Boundary wall blockwork below the tie beam is 100% complete and inspected. Shuttering is now 60% finished, with steel reinforcement placement scheduled to begin immediately upon completion of formwork.

  • 13-01-2026 — Site Visit — F/C2 (SHOPS) MBZC

    Construction update for Villa F-C2 in MBZC, Fujairah: Substructure works for the boundary wall are advancing rapidly. With PCC and neck columns completed, our team is currently executing solid blockwork in preparation for tie beam shuttering and casting.

  • 17-12-2025 — Site Visit — F/C2 (SHOPS) MBZC

    Construction update for F-C2 Shops: Following foundation completion, neck column casting is finalized. While progress is currently slowed by manpower issues, the team is focused on concrete repair for minor honeycombing identified during inspection. Preparations for the Tie Beam structural phase are now the immediate priority.