Project Tag: Block A, Plot 85 – Location: AHFARA


  • 12-01-2026 — Site Visit — A/85 AHFARA, FUJAIRAH

    Engineer Adeel Arif reports Villa A-85 Ahfara has reached a major milestone: Ground Floor plaster is complete, and 3 sides of outer wall bitumen are finished for upcoming stone works. The front decor slab is ready to cast, as inside plaster works continue on the stairs and first floor in Fujairah.

  • 05-01-2026 — Site Visit — A/85 AHFARA, FUJAIRAH

    Ground floor plaster near completion; first floor started. Bitumen works ongoing. Concealed flush tanks arrived on site in Fujairah.

  • 17-12-2025 — Site Visit — A/85 AHFARA, FUJAIRAH

    Progress report for Villa A-85 in Ahfara: Ground floor plaster works have reached 20% completion while first-floor MEP services remain in progress. The external boundary is advancing with the tie beam curing finalized. Simultaneously, the front villa decor blockworks are being installed to enhance the property’s architectural façade.

  • 13-12-2025 — Site Visit — A/85 AHFARA, FUJAIRAH

    Engineer Adeel Arif reports Villa A-85 Ahfara passed its final electrical inspection with the Owner and Consultant. Site approved to start plastering after minor fixes. Concealed fixtures installed, and Bitumen Works are underway before the external Stone Works.

  • 23-11-2025 — Site Visit — A/85 AHFARA, FUJAIRAH

    Site update for A-85 Ahfara: Boundary wall foundation and blockworks up to the tie beam are fully complete. Internal electrical works are ongoing, though the team is awaiting First Floor electrical drawings from the consultant. Site safety measures regarding water storage leakage have been enforced.