Progress report for Villa A-85 in Ahfara: Ground floor plaster works have reached 20% completion while first-floor MEP services remain in progress. The external boundary is advancing with the tie beam curing finalized. Simultaneously, the front villa decor blockworks are being installed to enhance the property’s architectural façade.
Engineer Adeel Arif reports Villa A-85 Ahfara passed its final electrical inspection with the Owner and Consultant. Site approved to start plastering after minor fixes. Concealed fixtures installed, and Bitumen Works are underway before the external Stone Works.
Site update for A-85 Ahfara: Boundary wall foundation and blockworks up to the tie beam are fully complete. Internal electrical works are ongoing, though the team is awaiting First Floor electrical drawings from the consultant. Site safety measures regarding water storage leakage have been enforced.
Engineer Adeel Arif reports on the successful concrete casting of the Boundary Wall Footing in Ahfara, Fujairah. The pour, supervised by Design Corner Engineering, involved strict QC checks, Oryxmix supply, and cube testing. Electrical work remains stopped due to payment issues.
Engineer Adeel Arif reports from Ahfara, Fujairah, that Boundary Wall Footing steel works are complete and Consultant-approved for casting. The critical bitumen sheet was verified at all joints. Internal electrical work remains stopped due to unresolved owner payment issues.