SITE VISIT REPORT: ACCELERATED MEP, WATERPROOFING & EXTERNAL FINISHES
Project Name: Proposed Villa Location: Block H, Plot 1311, Mohammed Bin Zayed City (MBZC), Fujairah Date of Visit: November 22, 2025 Time of Visit: 10:00 AM Report Prepared By: Engineer Adeel Arif (Site Engineer)
____________
I. Purpose of Visit:
To inspect the simultaneous progression of infrastructure installation (MEP/Plumbing) and crucial waterproofing applications, noting the overall site pace.
II. Observations & Progress Status:
The site is currently maintaining a good, high pace of work across multiple construction trades:
- Compound Wall Structure: The structural element is nearing completion, with the Top Beam casting remaining on one side of the perimeter wall.
- External MEP: Electric Pipe Work installation is actively ongoing within the Compound Wall structure.
- Internal MEP & Finishes:
- Plumbing Works (pipe installation) are advancing throughout the villa.
- Ceramic Works (tiling) are currently ongoing within the washrooms.
- Waterproofing: Comprehensive Waterproof Works are actively being applied across various areas of the villa structure (e.g., wet areas, roofs, slabs) as per specification.
- Front Facade: The Decor Blockworks Plaster application is ongoing at the front of the villa, preparing the exterior surface for final finishing.
III. Directives & Next Steps:
- Compound Wall Priority: Complete the remaining Top Beam casting immediately to structurally secure the entire perimeter.
- Finish Coordination: Ensure the completion of washroom ceramic works allows the final plumbing fixtures (taps, showerheads) to be installed promptly.
- Sustained Pace: Maintain the current good pace of work while upholding all quality control checks, especially for the critical waterproofing application.
IV. Concluding Remarks:
The project at H-1311, MBZC, is exhibiting excellent momentum, simultaneously closing out the structural compound wall and advancing critical internal (Plumbing, Ceramics) and protective (Waterproofing) elements. The current work pace should significantly contribute to meeting the project deadlines in Fujairah. For previous report click here.