SITE VISIT REPORT: FUJAIRAH MUNICIPALITY FINAL SLAB INSPECTION
Project Name: Proposed Villa G/420 Location: MBZC (Mohammed Bin Zayed City) Plot Number: G/420 Date of Inspection: October 23, 2025 Inspection Time: 10:30 AM Report Prepared By: Engineer Adeel Arif (Contractor Engineer)
____________
I. Inspection Summary:
The Fujairah Municipality (FM) inspection was conducted on the First Floor Slab to verify final readiness and compliance before granting the Concrete Casting Approval.
II. Attendees:
- FM Engineer: Engineer Riyad
- Consultant Engineer: Engineer Asif / International Designs Engineering Consultants
- Contractor Engineer: Engineer Adeel Arif
III. Observations & Compliance Findings:
| Item | Observation | Status |
| Punctuality & Presence | FM Engineer arrived promptly at 10:30 AM as scheduled. All required parties were present. | Compliant |
| Site Safety Measures | FM Engineer specifically acknowledged and appreciated the provision of the temporary external stairs with landing, along with the perimeter edge protection. | Compliant |
| Slab/Beam Rebar | Full inspection of all reinforcement, including bar counts, spacing, and lapping in the main slab and deep/inverted beams. | Compliant |
| Cover & Depth | Slab thickness and beam depth (including the inverted beam structure) were physically checked to ensure sufficient cover and accurate dimensioning. | Compliant |
| Necessary Steel Checks | All pre-casting quality checks (cleanliness, ties, block supports, etc.) were found to be satisfactory and acceptable. | Compliant |
IV. FM Directive & Contractor Action:
- Initial Discrepancy (Signboard):
- Upon arrival, the FM Engineer identified that the project signboard displayed a former ADIB logo at the top instead of the required Fujairah Municipality logo.
- The site was granted conditional approval for casting, pending the immediate correction of the signboard and uploading photographic evidence to the FM portal.
- Immediate Action (Engineer Adeel Arif):
- Directive Executed: I immediately directed the site team to modify the signboard to place the FM logo prominently at the top, ensuring full compliance with the updated regulation.
- Evidence Uploaded: The photograph of the rectified signboard was taken and instantly uploaded to the Fujairah Municipality online portal.
V. Final Approval:
- Following the successful submission and verification of the signboard correction, the Concrete Casting Approval was officially received from the Fujairah Municipality.
- The site is now fully authorized to proceed with the casting of the First Floor Slab.
If you want to visit previous report click here.