SITE VISIT REPORT: CONCURRENT FINISHES & EXTERIOR PAINT DECISION
Project Name: Proposed Villa Location: Block H, Plot 1311, Mohammed Bin Zayed City (MBZC), Fujairah Date of Visit: November 20, 2025 Time of Visit: 10:30 AM Report Prepared By: Engineer Adeel Arif (Site Engineer)
____________
I. Purpose of Visit:
To monitor the progress of simultaneous internal and external works, specifically structural elements, MEP installation, internal finishes, and to follow up on the exterior paint specification decision.
II. Observations & Concurrent Progress:
The project at H-1311, MBZC, is managing multiple trades efficiently:
- External Structure: The casting of the Compound Wall Top Beam is actively in progress, marking the structural completion of the perimeter enclosure.
- Internal Finishes: Ceramic Works (Tiling) in both the washrooms and the kitchen areas are nearing completion, preparing these wet areas for final fixture installation.
- MEP & Architectural: Inside the villa, Electrical Works (conduit and wiring) are ongoing, running simultaneously with the Outside Decor Block Works on the façade.
III. Critical Issue: Exterior Paint Specification Change
A critical decision affecting the exterior finishing timeline is pending:
- Original Contract: The contracted specification for the outer walls is National Epoxy paint.
- Owner Request: The Owner has requested to change the paint brand to Jotun, and there is consideration for upgrading to a textured finish (Epoxy or Grafi Decor), for which detailed cost variations have been provided.
- Action Required: The Owner must provide a final decision on the paint specification as quickly as possible, especially if the Grafi Decor option is chosen, as this requires an additional 25 working days.
IV. Concluding Remarks:
Villa H-1311 is progressing well, particularly with the near-completion of major ceramic tiling and the structural finalization of the Compound Wall. The prompt confirmation of the exterior paint choice (Jotun/Grafi Decor) is now the single most critical factor determining the start and completion schedule of all final exterior finishes. For previous report, click here.