Construction update for M-315 MBZC: A major milestone has been reached with the completion of blockworks for the whole villa. Internal walls are now fully prepped and ready for plaster. Simultaneously, construction of the parapet walls and roof-level decor works is actively ongoing.
Engineer Adeel Arif reports MBZC Plot 315 Block Work is accelerating, now 85% complete after new blocks arrived. An AC relocation in the Gents Majlis requires core cutting due to a missing AC sleeve, adding cost. Consultant informed Owner for decision.
Engineer Adeel Arif reports MBZC Plot 315 Block Work is 60% done. Focus on crack prevention using steel mesh at column joints and waterproof sheets on the First Floor slab. Work is slowed by a temporary block shortage in Fujairah.
Engineer Adeel Arif reports solid construction progress at MBZC Plot 315. Ground Floor Block Work is complete, and First Floor Block Work is advancing. Directive issued to accelerate block work construction speed to maintain project flow and meet deadlines in Fujairah.