Engineer Adeel Arif reports rapid progress at MBZC Villa H-1311. Ceramic fixing is 80% complete and outside paint works are underway. With kitchen decor and final electric and plumbing works in progress at great speed, the villa is nearing its final finishing stages in Fujairah.
Site update for MBZC Villa H-1311: Exterior painting has commenced alongside floor tile preparation and MEP progress. Engineer Adeel Arif has issued technical instructions regarding outer wall plaster alignment and crack repairs to ensure a premium finish for the final Jotun/Grafi Decor application.
Engineer Adeel Arif reports MBZC Villa H-1311 is nearing closure. Boundary Wall structure is complete and plastering is active. Windows Fitting, Roof Finishing Work, and final Electric Remaining Works are all in progress as the villa moves towards handover.
Engineer Adeel Arif reports rapid progress at MBZC Villa H-1311. Compound Wall beam casting and electric pipe work are ongoing alongside intensive plumbing and waterproof works. Ceramic works and decor plaster are advancing rapidly in Fujairah.
Engineer Adeel Arif reports simultaneous progress at MBZC Plot H-1311. Compound Wall Top Beam casting is underway alongside electrical works and near-complete ceramic works. The critical decision for Jotun Grafi Decor exterior paint is pending Owner approval.