Update for Villa F-C2, MBZC: Boundary wall blockwork below the tie beam is 100% complete and inspected. Shuttering is now 60% finished, with steel reinforcement placement scheduled to begin immediately upon completion of formwork.
Construction update for Villa F-C2 in MBZC, Fujairah: Substructure works for the boundary wall are advancing rapidly. With PCC and neck columns completed, our team is currently executing solid blockwork in preparation for tie beam shuttering and casting.
Construction update for F-C2 Shops: Following foundation completion, neck column casting is finalized. While progress is currently slowed by manpower issues, the team is focused on concrete repair for minor honeycombing identified during inspection. Preparations for the Tie Beam structural phase are now the immediate priority.
Engineer Adeel Arif reports F-C2 Shops MBZC has completed foundation casting and is preparing for block work and neck column shuttering. The site is currently idle with no labor present. Urgent directives issued to speed up works and clean the site to meet the Fujairah construction deadline.
Engineer Adeel Arif reports the MBZC Shops Building foundation, cast on Nov 15th, is now undergoing curing and de-shuttering. Only minor hairline cracks observed, confirming a successful pour. Focus remains on proper concrete curing in Fujairah.