Project Tag: Block F, Plot 154 – Location: Mohamed Bin Zayed City


  • 12-11-2025 — Site Visit — F/154 MBZC

    Engineer Adeel Arif reports MBZC Plot 154 block work is 90% complete. Owner approval of the wall layout is now requested to proceed. Waterproofing sheets for the First Floor are delayed, and work remains slowed by the Fujairah block shortage.

  • 10-11-2025 — Site Visit — F/154 MBZC

    Engineer Adeel Arif reports block work advancement at MBZC Plot 154, Fujairah. GF Block Work is 80% complete, and Lintel Beams are being cast. Progress is slowed by a Fujairah blockwork shortage, demanding logistical solutions.

  • 06-11-2025 — Site Visit — F/154 MBZC

    Engineer Adeel Arif reports block work advancing at MBZC Plot 154, Fujairah. Ground Floor Block Work is 60% complete, and First Floor Block Work has commenced. Directives issued to ensure strict adherence to the minimum 15 mm mortar thickness for structural compliance.