Engineer Adeel Arif reports MBZC Plot 154 block work is 90% complete. Owner approval of the wall layout is now requested to proceed. Waterproofing sheets for the First Floor are delayed, and work remains slowed by the Fujairah block shortage.
Engineer Adeel Arif reports block work advancement at MBZC Plot 154, Fujairah. GF Block Work is 80% complete, and Lintel Beams are being cast. Progress is slowed by a Fujairah blockwork shortage, demanding logistical solutions.
Engineer Adeel Arif reports block work advancing at MBZC Plot 154, Fujairah. Ground Floor Block Work is 60% complete, and First Floor Block Work has commenced. Directives issued to ensure strict adherence to the minimum 15 mm mortar thickness for structural compliance.