Project Tag: Block F, Plot 154 – Location: Mohamed Bin Zayed City


  • 27-11-2025 — Site Visit — F/154 MBZC

    Engineer Adeel Arif reports on F-154 MBZC progress. Ground floor block work is nearing completion (99%), while the first floor is 20% done. Key compliance measures, including steel mesh installation every 3rd layer and waterproof sheets, are being strictly followed per Fujairah Municipality rules.

  • 24-11-2025 — Site Visit — F/154 MBZC

    Construction update for F-154 MBZC: Blocks have arrived, marking the start of First Floor blockworks. Shuttering for the remaining Ground Floor lintel beams is in progress. The site has received waterproofing materials and an increased labour force to ensure rapid project completion.

  • 18-11-2025 — Site Visit — F/154 MBZC

    Engineer Adeel Arif reports on stalled progress at MBZC Plot 154, Fujairah. GF Block Work is near completion, but a critical, month-long block shortage and labor shortage persist. Owner approval of the First Floor layout is awaited to proceed.

  • 12-11-2025 — Site Visit — F/154 MBZC

    Engineer Adeel Arif reports MBZC Plot 154 block work is 90% complete. Owner approval of the wall layout is now requested to proceed. Waterproofing sheets for the First Floor are delayed, and work remains slowed by the Fujairah block shortage.

  • 10-11-2025 — Site Visit — F/154 MBZC

    Engineer Adeel Arif reports block work advancement at MBZC Plot 154, Fujairah. GF Block Work is 80% complete, and Lintel Beams are being cast. Progress is slowed by a Fujairah blockwork shortage, demanding logistical solutions.