Project Tag: Block F, Plot 154 – Location: Mohamed Bin Zayed City


  • 14-01-2026 — Site Visit — F/154 MBZC

    Post Excerpt (Social Media/Blog Summary): Progress update for Villa F-154 in MBZC, Fujairah: Ground floor plastering is 100% complete, roof parapets are finished, and owner-requested boundary wall modifications, including a new straight tie beam, are now finalized. The project is now transitioning to first-floor internal finishes.

  • 17-12-2025 — Site Visit — F/154 MBZC

    Site Update for Villa F-154: First floor blockworks have reached 80% completion with ongoing parapet masonry. Internal MEP works are running concurrently to ensure project efficiency. focus has shifted to the external perimeter, where steel reinforcement for the boundary wall is in progress, preparing for column casting.

  • 13-12-2025 — Site Visit — F/154 MBZC

    Engineer Adeel Arif reports MBZC Villa F-154 Ground Floor Block Work is 100% complete. Site momentum is high: First Floor Block Work is 50% done, with FF Lintel Beams being casted. GF Electrical Pipe Works are actively in progress in Fujairah.

  • 27-11-2025 — Site Visit — F/154 MBZC

    Engineer Adeel Arif reports on F-154 MBZC progress. Ground floor block work is nearing completion (99%), while the first floor is 20% done. Key compliance measures, including steel mesh installation every 3rd layer and waterproof sheets, are being strictly followed per Fujairah Municipality rules.

  • 24-11-2025 — Site Visit — F/154 MBZC

    Construction update for F-154 MBZC: Blocks have arrived, marking the start of First Floor blockworks. Shuttering for the remaining Ground Floor lintel beams is in progress. The site has received waterproofing materials and an increased labour force to ensure rapid project completion.