Site Update for Villa F-154: First floor blockworks have reached 80% completion with ongoing parapet masonry. Internal MEP works are running concurrently to ensure project efficiency. focus has shifted to the external perimeter, where steel reinforcement for the boundary wall is in progress, preparing for column casting.
Engineer Adeel Arif reports MBZC Villa F-154 Ground Floor Block Work is 100% complete. Site momentum is high: First Floor Block Work is 50% done, with FF Lintel Beams being casted. GF Electrical Pipe Works are actively in progress in Fujairah.
Engineer Adeel Arif reports on F-154 MBZC progress. Ground floor block work is nearing completion (99%), while the first floor is 20% done. Key compliance measures, including steel mesh installation every 3rd layer and waterproof sheets, are being strictly followed per Fujairah Municipality rules.
Construction update for F-154 MBZC: Blocks have arrived, marking the start of First Floor blockworks. Shuttering for the remaining Ground Floor lintel beams is in progress. The site has received waterproofing materials and an increased labour force to ensure rapid project completion.
Engineer Adeel Arif reports on stalled progress at MBZC Plot 154, Fujairah. GF Block Work is near completion, but a critical, month-long block shortage and labor shortage persist. Owner approval of the First Floor layout is awaited to proceed.