SITE VISIT REPORT: BLOCK DELIVERY CONFIRMATION & WORK ACCELERATION

Project Name: Proposed Villa Location: Block G, Plot 425, Mohammed Bin Zayed City (MBZC), Fujairah Date of Visit: December 14, 2025 Time of Visit: 9:30 AM Report Prepared By: Engineer Adeel Arif (Site Engineer)

____________

I. Purpose of Visit:

To confirm the long-awaited delivery of the essential block materials, officially restart construction activities, and implement measures to recover lost time.

II. Observations & Progress Status:

  • Previous Status: Following the successful footing casting, the project entered an unscheduled holding period. Work had been stopped for many days due to a severe supply chain issue.
  • Material Resolution: We confirm that the required batch of solid blocks has finally arrived on site after a significant and prolonged delay from the supplier.
  • Current Action: With the arrival of the blocks, preparations for the immediate commencement of the Ground Floor block work are underway.

III. Directives & Remedial Actions:

  • Work Acceleration: The site team has been instructed to accelerate the work and proceed at maximum capacity to minimize the impact of the multi-day delay caused by the late block arrival.
  • Supply Chain Management: Moving forward, rigorous follow-up is mandated for all critical material orders to prevent a recurrence of this kind of stoppage.

IV. Concluding Remarks:

The critical supply bottleneck at MBZC Villa G-425 has been resolved. The late arrival of the solid blocks significantly impacted the immediate transition post-footing casting, but the project is now ready to recommence wall construction. The priority for the coming days is strict adherence to the accelerated schedule to compensate for the downtime and regain construction momentum in Fujairah. For previous report click here.