SITE VISIT REPORT: FUJAIRAH MUNICIPALITY FINAL SLAB INSPECTION

Project Name: Proposed Villa G/420 Location: MBZC (Mohammed Bin Zayed City) Plot Number: G/420 Date of Inspection: October 23, 2025 Inspection Time: 10:30 AM Report Prepared By: Engineer Adeel Arif (Contractor Engineer)

____________

I. Inspection Summary:

The Fujairah Municipality (FM) inspection was conducted on the First Floor Slab to verify final readiness and compliance before granting the Concrete Casting Approval.

II. Attendees:

  • FM Engineer: Engineer Riyad
  • Consultant Engineer: Engineer Asif / International Designs Engineering Consultants
  • Contractor Engineer: Engineer Adeel Arif

III. Observations & Compliance Findings:

ItemObservationStatus
Punctuality & PresenceFM Engineer arrived promptly at 10:30 AM as scheduled. All required parties were present. Compliant
Site Safety MeasuresFM Engineer specifically acknowledged and appreciated the provision of the temporary external stairs with landing, along with the perimeter edge protection. Compliant
Slab/Beam RebarFull inspection of all reinforcement, including bar counts, spacing, and lapping in the main slab and deep/inverted beams. Compliant
Cover & DepthSlab thickness and beam depth (including the inverted beam structure) were physically checked to ensure sufficient cover and accurate dimensioning.Compliant
Necessary Steel ChecksAll pre-casting quality checks (cleanliness, ties, block supports, etc.) were found to be satisfactory and acceptable. Compliant

IV. FM Directive & Contractor Action:

  • Initial Discrepancy (Signboard):
    • Upon arrival, the FM Engineer identified that the project signboard displayed a former ADIB logo at the top instead of the required Fujairah Municipality logo.
    • The site was granted conditional approval for casting, pending the immediate correction of the signboard and uploading photographic evidence to the FM portal.
  • Immediate Action (Engineer Adeel Arif):
    • Directive Executed: I immediately directed the site team to modify the signboard to place the FM logo prominently at the top, ensuring full compliance with the updated regulation.
    • Evidence Uploaded: The photograph of the rectified signboard was taken and instantly uploaded to the Fujairah Municipality online portal.

V. Final Approval:

  • Following the successful submission and verification of the signboard correction, the Concrete Casting Approval was officially received from the Fujairah Municipality.
  • The site is now fully authorized to proceed with the casting of the First Floor Slab.

If you want to visit previous report click here.